BHP Plans Up to $18 Billion Push to Double South Australian Copper Output by 2040
SentiSense · Published · Updated
BHP said on Monday it plans to double copper production at its Copper South Australia business, targeting about 500,000 tonnes a year by 2035 and about 650,000 tonnes by 2040, at a cost Reuters put at up to $18.1 billion. The plan, unveiled at a two-day investor site tour, stages final investment decisions from late 2027, starting with a smelter and refinery expansion.
BHP laid out a plan on Monday to double copper production at its Copper South Australia business by 2040, targeting about 500,000 tonnes a year by 2035 and about 650,000 tonnes a year by 2040. Reuters put the cost at up to $18.1 billion. The targets were presented at a two-day investor and analyst site tour of the South Australian assets on 23-24 November.
The plan is staged rather than a single commitment. In its investor materials BHP lists a Prominent Hill expansion of about US$0.9 billion due to commission in December 2026, a smelter and refinery expansion of US$3.2-4.1 billion with a final investment decision targeted for the second half of 2027, a Carrapateena expansion of US$1.8-2.1 billion (decision in the first half of 2028) and Olympic Dam mine and concentrator growth of US$4.1-5.4 billion (decision in 2029). BHP describes the move to two-stage smelting as essential to unlocking Olympic Dam's reserves. A second phase built around the Ankata deposit, formerly Oak Dam, or Olympic Dam Deeps carries a further US$4.5-5.8 billion estimate, with a decision not expected until 2032.
BHP frames Copper SA as core to lifting its attributable copper production by about 40% by the mid-2030s, from about 1.4 million tonnes a year today toward about 2 million tonnes. It guides to a phase-one internal rate of return of 14-17% and cumulative free cash flow of about US$9 billion to 2035. Kalkine reported the shares added nearly 2% on Monday.
What to watch: the smelter decision in late 2027 is the first large capital commitment, and each later stage still depends on study results and board approval. Copper prices over that window, and cost discipline on projects with ten-year horizons, will decide whether the targets hold.